The trusses are all on, and the roof has been started.  This week the gutters, fascia and roof itself will be installed, so things are really starting to happen.

As far as the wiring is going, Dad and I are just about finished.  It has been a big job though... much bigger than I expected, and we have used a mammoth amount of cable.  If I get a chance I might work out exactly how much, but it would be at least a few kilometers.

Below are some pictures of the roof as of today.

View of the roof trusses from the park carpark above us

Bit hard to get a good idea of what the side is going to look like with the scaffolding up.

Very happy with how the roof is looking... 




Looking down the left side. The overhanging bit there is the powder room.

Another shot of the powder room and the left, entry hallway window on the right.

Deck has been started


Those posts are quite large and heavy.  John said it was quite an effort getting those in place. as they are a single post going from the ground to the top roof.